Tomingley

The Project

The New Tomingley Gold Mine project, valued at $19M, was undertaken for Tomingley Gold Operations Pty Ltd in Tomingley, NSW between 2012 and 2013. The services provided included Civil Works and Plant Hire.
Client
Tomingley Gold Operations Pty Ltd
Duration
2012 - 2013
Location
Tomingley, NSW
Services
Civil Works, Plant Hire

The Scope

Construction of new gold mine and overburden strip, as follows:

  • 750,000m3 of Bulk and Detailed Earthworks
  • Construction of hardstand, plant area and laydown facilities
  • Access roads
  • Site drainage including culverts
  • Pavements
  • Bunds and earthern berms to redirect storm water
  • Construction of a new Tailings Dam Facility
  • Construction of raw water ponds for reticulation of the system
  • Overburden strip of the 3 main pits onsite
  • Construction of ROM Pad
  • All preliminary Site Earthworks. Construction of Tailings Dam including Dam Lining

Other A1 Earthworx Projects

William Maker Drive

River Street West

Cotter Dam

Explore all our works

Let's chat about your project

This website uses cookies for analytics and to improve web experience.